GanttView.AllowSchedulingOnEditing Property
Gets or sets whether the GanttControl should recalculate task properties once a related task’s start date, progress, or duration has been modified. This is a dependency property.
Namespace: DevExpress.Xpf.Gantt
Assembly: DevExpress.Xpf.Gantt.v25.1.dll
NuGet Package: DevExpress.Wpf.Gantt
Declaration
Property Value
| Type | Description |
|---|---|
| Boolean | true, to recalculate task properties; otherwise, false. |
Remarks
The GanttControl recalculates related task positions and updates the summary task positions, durations, and progress when you change a task’s start date, progress, or duration.

This functionality is available via the following API:
| Member | Description |
|---|---|
| AllowSchedulingOnEditing | If enabled, the control re-schedules tasks after each change. |
| GanttView.ScheduleMode | A schedule mode (Forward or Backward) that specifies how the GanttControl recalculates task properties. |
| ScheduleTask / ScheduleDependentTasks | Call these methods to re-schedule tasks on demand if the previous option is disabled. |
| ScheduleAll() | Call this method to re-schedule all the Gantt tasks. |
| TasksScheduled | This event allows you to rollback changes if they create invalid links. |
| DeleteTask(TreeListNode) | Use this method to delete a task and re-schedule the affected tasks. |