  • GanttView.AllowSchedulingOnEditing Property

    Gets or sets whether the GanttControl should recalculate task properties once a related task’s start date, progress, or duration has been modified. This is a dependency property.

    Namespace: DevExpress.Xpf.Gantt

    Assembly: DevExpress.Xpf.Gantt.v26.1.dll

    NuGet Package: DevExpress.Wpf.Gantt

    Declaration

    public bool AllowSchedulingOnEditing { get; set; }

    Property Value

    Type Description
    Boolean

    true, to recalculate task properties; otherwise, false.

    Remarks

    The GanttControl recalculates related task positions and updates the summary task positions, durations, and progress when you change a task’s start date, progress, or duration.

    Gantt automatic

    This functionality is available via the following API:

    Member Description
    AllowSchedulingOnEditing If enabled, the control re-schedules tasks after each change.
    GanttView.ScheduleMode A schedule mode (Forward or Backward) that specifies how the GanttControl recalculates task properties.
    ScheduleTask / ScheduleDependentTasks Call these methods to re-schedule tasks on demand if the previous option is disabled.
    ScheduleAll() Call this method to re-schedule all the Gantt tasks.
    TasksScheduled This event allows you to rollback changes if they create invalid links.
    DeleteTask(TreeListNode) Use this method to delete a task and re-schedule the affected tasks.