GanttView.BaselineFinishDateMapping Property
Provides a path to a data field that stores the task baseline’s finish date. This is a dependency property.
Namespace: DevExpress.Xpf.Gantt
Assembly: DevExpress.Xpf.Gantt.v24.1.dll
NuGet Package: DevExpress.Wpf.Gantt
Declaration
Property Value
Type | Description |
---|---|
Mapping | A Mapping object indicating the data field and the converter. |
Remarks
Use the BaselineFinishDateMapping property to bind the Gantt item’s GanttNode.BaselineFinishDate property to a data field. The data field is obtained from the data source specified by the GanttControl’s ItemsSource property.
Tip
Use the Mapping.Converter property to register a value converter for a custom storing format.
You can specify mapping as a Mapping markup extension object or string. The code sample below illustrates how to map Gantt items’ properties to data source fields.
<dxgn:GanttControl ItemsSource="{Binding Tasks}">
...
<dxgn:GanttControl.View>
<dxgn:GanttView
KeyFieldName="Id"
ParentFieldName="ParentId"
NameMapping="{dxgn:Mapping Name}"
StartDateMapping="StartDate"
FinishDateMapping="{dxgn:Mapping FinishDate}"
ProgressMapping="Progress"
BaselineStartDateMapping="BaselineStartDate"
BaselineFinishDateMapping="BaselineFinishDate"
PredecessorLinksPath="Links">
<dxgn:GanttView.PredecessorLinkMappings>
<dxgn:GanttPredecessorLinkMappings Task="Id" PredecessorTask="PredecessorId"/>
</dxgn:GanttView.PredecessorLinkMappings>
</dxgn:GanttView>
</dxgn:GanttControl.View>
</dxgn:GanttControl>