  • GanttView.AllowTaskMove Property

    Gets or sets whether an end user can edit task start and finish dates by moving tasks alongside the timeline. This is a dependency property.

    Namespace: DevExpress.Xpf.Gantt

    Assembly: DevExpress.Xpf.Gantt.v26.1.dll

    NuGet Package: DevExpress.Wpf.Gantt

    Declaration

    public bool? AllowTaskMove { get; set; }

    Property Value

    Type Description
    Nullable<Boolean>

    true, if an end user can move tasks alongside the timeline; otherwise, false.

    Remarks

    When the AllowTaskMove property is set to null, the ability to change the task start and finish dates depends on the AllowEditing property value.

    The task duration is a working time duration. When an end user moves task, the task duration does not change, but the calendar duration (FinishDate - StartDate) may be different.