GanttView.AllowTaskMove Property
Gets or sets whether an end user can edit task start and finish dates by moving tasks alongside the timeline. This is a dependency property.
Namespace: DevExpress.Xpf.Gantt
Assembly: DevExpress.Xpf.Gantt.v24.1.dll
NuGet Package: DevExpress.Wpf.Gantt
Declaration
Property Value
Type | Description |
---|---|
Nullable<Boolean> | true, if an end user can move tasks alongside the timeline; otherwise, false. |
Remarks
When the AllowTaskMove property is set to null, the ability to change the task start and finish dates depends on the AllowEditing property value.
The task duration is a working time duration. When an end user moves task, the task duration does not change, but the calendar duration (FinishDate - StartDate) may be different.
See Also