GanttView.ScheduleDependentTasks(TreeListNode) Method

Re-schedules Gantt tasks that depend on the specified task on demand.

Namespace: DevExpress.Xpf.Gantt

Assembly: DevExpress.Xpf.Gantt.v20.1.dll

Declaration

public void ScheduleDependentTasks(
    TreeListNode node
)
Public Sub ScheduleDependentTasks(
    node As TreeListNode
)

Parameters

Name Type Description
node TreeListNode

A Gantt task whose dependant tasks should be re-scheduled.

Remarks

The GanttControl recalculates related task positions and updates the summary task positions, durations, and progress when you change a task's start date, progress, or duration.

Gantt automatic

This functionality is available via the following API:

Member Description
AllowSchedulingOnEditing If enabled, the control re-schedules tasks after each change.
GanttView.ScheduleMode A schedule mode (Forward or Backward) that specifies how the GanttControl recalculates task properties.
ScheduleTask / ScheduleDependentTasks Call these methods to re-schedule tasks on demand if the previous option is disabled.
ScheduleAll() Call this method to re-schedule all the Gantt tasks.
TasksScheduled This event allows you to rollback changes if they create invalid links.