    Fires when a task’s finish date is successfully modified. This event only fires when a user modifies a task in the chart. When the user modifies a task in the task list, the event does not fire.

    Namespace: DevExpress.XtraGantt

    Assembly: DevExpress.XtraGantt.v25.1.dll

    NuGet Package: DevExpress.Win.Gantt

    Declaration

    [DXCategory("Events")]
    public event TaskFinishModifiedEventHandler TaskFinishDateModified

    Event Data

    The TaskFinishDateModified event's data class is TaskFinishModifiedEventArgs. The following properties provide information specific to this event:

    Property Description
    OriginalTaskFinish Gets the processed task’s original (before the operation) finish date.
    ProcessedNode Gets the modified node. Inherited from TaskModificationEventArgs.
    ProcessedTask Gets the modified task. Inherited from TaskModificationEventArgs.
    TaskSplitInfo Gets information about segments of the processed split task. Inherited from TaskModificationEventArgs.

    Remarks

    If the AllowModifyTasks option is enabled, users can reschedule a task. Users can use the mouse pointer to resize its duration or drag it to a new time slot.

    image

    To resize a task, move the mouse pointer over a task’s edge.

    image

    Note

    The Editable option must be enabled and the ReadOnly option must be disabled to allow users to modify tasks.

    You can handle the following events to customize an operation: