GanttControl.TaskProgressModificationStarted Event

Fires when a user starts to modify a task’s progress. This event only fires when a user modifies a task in the chart. When the user modifies a task in the task list, the event does not fire.

Namespace: DevExpress.XtraGantt

Assembly: DevExpress.XtraGantt.v24.2.dll

NuGet Package: DevExpress.Win.Gantt

#Declaration

[DXCategory("Events")]
public event TaskProgressModificationEventHandler TaskProgressModificationStarted

#Event Data

The TaskProgressModificationStarted event's data class is TaskProgressModificationEventArgs. The following properties provide information specific to this event:

Property Description
CurrentProgress Gets or sets the processed task’s current (during the operation) progress.
OriginalProgress Gets the processed task’s original (before the operation) progress.
ProcessedNode Gets the modified node. Inherited from TaskModificationEventArgs.
ProcessedTask Gets the modified task. Inherited from TaskModificationEventArgs.
TaskSplitInfo Gets information about segments of the processed split task. Inherited from TaskModificationEventArgs.

#Remarks

If the AllowModifyProgress option is enabled, users can update a task’s progress.

image

Note

The Editable option must be enabled and the ReadOnly option must be disabled to allow users to modify tasks.

You can handle the following events to customize an operation:

See Interactive Editing for more information.