GanttView.AllowSchedulingOnEditing Property
Gets or sets whether the GanttControl should recalculate task properties once a related task’s start date, progress, or duration has been modified. This is a dependency property.
Namespace: DevExpress.Xpf.Gantt
Assembly: DevExpress.Xpf.Gantt.v19.1.dll
Declaration
Property Value
Type | Description |
---|---|
Boolean | true, to recalculate task properties; otherwise, false. |
Remarks
Once a task’s start date, progress, or duration has been modified, the GanttControl can recalculate related task positions and update the summary task positions, durations, and progress.
This functionality is available via the following API:
Member | Description |
---|---|
AllowSchedulingOnEditing | If enabled, the control re-schedules tasks after each task’s start date, progress, or duration modification. |
ScheduleNode/ScheduleDependentNodes | Call these methods to re-schedule tasks on demand if the previous option is disabled. |
ScheduleAll() | Call this method to re-schedule all the Gantt tasks. |
TasksScheduled | This event allows you to rollback the edit changes if they have become the reason for invalid links. |
DeleteTask(TreeListNode) | Use this method to delete a task and re-schedule the affected tasks. |