Skip to main content
A newer version of this page is available. .

PredecessorLinkType Enum

Lists the values used to specify the Gantt task relationships.

Namespace: DevExpress.Mvvm.Gantt

Assembly: DevExpress.Mvvm.v19.1.dll

Declaration

public enum PredecessorLinkType

Members

Name Description
FinishToStart

The successor task may not start before the predecessor task is finished.

FinishToFinish

The successor task may not finish before the predecessor task is finished.

StartToStart

The successor task may not start before the predecessor task is started.

StartToFinish

The successor task may not finish before the predecessor task is started.

Related API Members

The following properties accept/return PredecessorLinkType values:

Library Related API Members
Cross-Platform Class Library GanttPredecessorLink.LinkType
WPF Controls AddingNewPredecessorLinkEventArgs.LinkType
GanttConnector.PredecessorLinkType

Remarks

The GanttControl can show relationships between tasks. These relationships are called task dependencies. They indicate dependency criteria based on which tasks begin and end in relation to each other. For example, the FinishToStart dependency means that the second task may not start before the first task is finished.

The following code snippet (auto-collected from DevExpress Examples) contains a reference to the PredecessorLinkType enum.

Note

The algorithm used to collect these code examples remains a work in progress. Accordingly, the links and snippets below may produce inaccurate results. If you encounter an issue with code examples below, please use the feedback form on this page to report the issue.

See Also